SIRTE III UREA PRODUCTION UNIT

Points of View :
  •  
Basic Information
  •  
CHEMICALS
  •  

Production Requirements

  •  
Labors

 

Basic Information

 

  •  
Design Capacity : 1750 Ton/day
  •  
Production Capacity : 1802 Ton/day
  •  
Technology : STAMICARBOM
  •  
Construction Engineering Company  : UHDE
  •  
 Start up Date : December 1983

 

Back To Top

 

CHEMICALS

 

Unit Process Chemicals Manufacturing Company vendor Company
  LSN-39 NALCO  
  Calcium Setrite    
  HMT    

 

Back To Top

 

 

 

Production Requirements

 

 

actual consumption rate per produced ton

Unit
Saturated  Steam

0.93

 TON

Super Heated Steam

1.35

TON

WATER BOILER (LOW PRESSURE)  none  
WATER BOILER (HIGH PRESSURE)     
PROCESS WATER    

ELECTRICITY

20

KWH

FUEL : NATURAL GAS - LQUID FUEL

103

NM3

   Back To Top 

 

 

 

LABORS

 

 

Number of employee in urea production Unit= 49

  •  

  Graduated 

 = 6
  •  

Technicians 

 = 45
  •  

Workers

 = 5